• 24/7 emergency response
  • Toronto & the GTA
Service area

Condominium Plumbing in Etobicoke

From the 1970s slab towers along Mill Road and Markland Wood to the newer buildings at Humber Bay Shores, Etobicoke's condominium stock spans fifty years. We work across all of it.

Opened suite wall in an Etobicoke condominium showing branch supply piping and new isolation valves installed by BMI before the wall is closed
Water utility
Toronto Water
Municipality
City of Toronto
Common scope
Riser and fan coil replacement
Emergency response
24/7, every day
The stock

Fifty years of building stock, at opposite ends of their service life

Etobicoke's condominium buildings fall into two groups that have almost nothing in common mechanically, and knowing which one a building belongs to tells you most of what its plumbing is going to need.

The 1970s towers

Mill Road, Markland Wood, the Kipling and Islington corridors: concrete slab towers, hydronic heating and cooling through in-suite fan coils, and original copper and steel risers now past fifty years old. This is where capital work lives. Leaks begin repeating on the same stack, fan coils reach the end of their service life at the same time as the risers feeding them, and the gate valves have been sitting untouched since commissioning. Doing the riser and the fan coil in one shutdown, as we did at 299 Mill Road, is substantially cheaper than doing them as two projects five years apart.

Humber Bay Shores and the newer stock

The waterfront towers and the Islington City Centre buildings are a different proposition. Their pipe is not the problem yet. What comes up instead is pressure reducing valve stations serving multiple zones in tall buildings, in-suite pipe from the Kitec era needing identification and removal, and kitchen stacks that were never put on a cleaning schedule and are restricted with grease well before anyone expected it.

What applies to both

Valve audits. A new building's valves seize just as thoroughly as an old one's if nobody turns them, and the cost of finding that out during an emergency is the same in either.

New copper mains and isolation valves installed by BMI in a condominium mechanical room, replacing original steel distribution piping
New mains and isolation in a mechanical room. In a fifty-year-old building this is usually where a programme starts.
What we do here

The work we are called into Etobicoke buildings for

Risers and fan coils

Replaced together in one shutdown where both are of the same vintage, which in the 1970s stock they usually are. Riser replacement.

Kitec removal

Identified properly before anyone quotes a building, then re-piped in copper suite by suite. Kitec replacement.

Valve work

Seized isolation located, replaced and charted, so the next repair is one suite rather than the whole building. Valve replacements.

Kitchen stacks

Grease-restricted stacks cleaned on a schedule before the first lower-floor backup rather than after it. Kitchen stack cleaning.

Camera inspection

A written condition report on stacks and drains, which is what a reserve fund study should be built on. Camera pipe inspection.

Emergencies

Answered at any hour by someone who can dispatch a crew, not take a message. 24/7 emergency response.

Completed projects

Etobicoke work we have completed

Riser and fan coil replacement at 299 Mill Road, delivered suite by suite with the tower occupied throughout.

299 Mill Rd, Etobicoke - 436-unit condominium where BMI replaced risers ahead of schedule Riser & Fan Coil Replacement

299 Mill Rd

Etobicoke, Ontario · 436 units

Riser replacement across 436 units including asbestos abatement and air-quality testing throughout. Delivered two months ahead of the eight-month schedule.

At a glance

Condominium plumbing in Etobicoke

How BMI works in Etobicoke condominium and multi-residential buildings.
Area coveredAll of Etobicoke, including Humber Bay Shores, Islington City Centre, Markland Wood, Kipling and Rexdale
MunicipalityCity of Toronto, amalgamated 1998
Water utilityToronto Water
Office356 Marlee Ave, Toronto
Completed here299 Mill Rd, riser and fan coil replacement
Older stock1970s towers: risers, fan coils, valves and stacks at end of service life
Newer stockPressure reducing valve zones, Kitec-era in-suite pipe, kitchen stack cleaning
ComplianceBackflow prevention testing to City of Toronto requirements
ResidentsStay in their homes throughout
Emergency response24/7, (416) 845-3756
Questions

Etobicoke condominium questions

Yes. Etobicoke was amalgamated into the City of Toronto on 1 January 1998, so Toronto Water is the utility, permits come from the City of Toronto, and the City's backflow prevention testing requirements apply the same way they do anywhere else in the city. For a board, the practical effect is that compliance paperwork and the programmes behind it are identical to a downtown corporation's.

A fan coil is the unit inside the suite that heats and cools it, fed by the building's heating and cooling risers. It comes up alongside riser replacement because the two share the same shutdown and the same opened wall: once the riser is exposed and the water is off on that stack, replacing a fan coil that is at the end of its life costs a fraction of what it costs to come back and do it as a separate project later. That is how we scoped 299 Mill Road, and it is usually the right call when both systems are of the same vintage.

They are mostly 1970s construction, which puts the original risers, valves and fan coils past fifty years. At that age the failure pattern changes: leaks start repeating on the same stack rather than appearing at random, and isolation valves that have never been turned no longer close when somebody needs them to. Those two things together are what turn a one-suite repair into a building-wide shutdown, which is why we push valve audits in this stock even ahead of the riser conversation.

Different age, different problems. Pipe age is not the issue in buildings finished in the last twenty years, but tall waterfront towers run multiple pressure zones, so pressure reducing valve stations matter more and drift in one is felt across a whole zone. Kitchen stacks are the other recurring item: a building that has never had its stacks on a cleaning schedule will have grease restriction regardless of how new it is, and the first sign is usually a backup in a lower-floor suite.

Yes, and that is how 299 Mill Road was done. Work is phased stack by stack, so water is off on a small group of suites on their scheduled day while the rest of the building carries on. Residents stay in their homes for the whole programme. Each suite gets written notice with a date and a window, the new pipe is pressure tested before anything is closed, and our own finishing crew boards, tapes, sands and paints the wall rather than leaving it for a separate trade to schedule.

The phone is answered at any hour by someone who can dispatch a crew rather than take a message, which is the part that decides how long a flood runs. We are based at 356 Marlee Avenue in Toronto, so Etobicoke is a straightforward run outside of rush hour. Where we already hold a maintenance contract we also hold the building's valve chart, so the crew knows where the isolation is before it arrives.

Have a plumbing problem in an Etobicoke building?

Send us the scope and we will come and look at the building before we quote it. Emergencies are answered at any hour.

Burst pipe or active leak right now? We answer 24 hours a day, every day of the year — (416) 845-3756
Call now Book Now